Option 1 : For rough estimate by using thumb rule you can use 90kg per cubic meter. Example the quantity of concrete is 10 cubic meter, the required rebar is 90 kg.
Option 2 : If you need accurate quantity, you need to count as per the detailed construction drawing. ☺